| Clifton
Cay, New Providence Island (Nassau), Bahamas
1998: Design
of beach enhancement along 8,000-ft shoreline, including two community
beach parks with |
||
|
Cocoa
Beach, Florida
1996: 40,000 c.y. truck-haul placed on 5000 ft of downtown shorefront as interim beach nourishment measure. Design, permitting, construction-review, Engineer-of-Record. Client: Canaveral Port Authority. |
![]() |
|
![]() |
1991:
25,000 c.y. of imported Bahamian |
|
|
Frozen
& Alder Cay, Bahamas
1994-01: Reclamation of relic salt pond to create 3-acre swim-in lagoon with beaches and coral/fish aquaria. Design, construction review, Engineer of Record. Client: Private development. |
![]() |
|
![]() |
Ft.
Clinch, Nassau County, Florida 2001: Rehabilitation of historical rock groins, construction of new T-head groins, and placement of sand for beach enhancement at a historic preservation site (c. 1880s). Design, permitting, construction review. Client: Florida Park Service. |
|